Supply Forecasting & Notice of Shipment (NOS) Verification Procedures - Section 12
12.0 Appendix
12.1 Supply Forecasting Process (Process Flow Diagram)
12.2 Notice of Shipment to Delivery Verification Process (Process Flow Diagram)
12.3 Form A Example (Forecast of Crude Oil & Condensate Delivery Volumes)
span>
Alberta - Form A span>
span>
British Columbia - Form A span>
span>
Saskatchewan - Form A span>
span>
Manitoba - Form A span>
12.4 Form B Example (Forecast of Crude Oil & Condensate Delivery Volumes to Shipper)
span>
Alberta - Form B span>
span>
British Columbia - Form B span>
span>
Saskatchewan - Form B span>
span>
Manitoba - Form B span>
12.5 Notice of Shipment Form (Example)
Notice of Shipment Form (Example)
12.6 Deviation Codes
(These can be found on the Form A and B)
| Code Explanation | Main Reason For Change |
|---|---|
| 01 | Production Increase - New Well |
| 02 | Production Increase - Well Workover |
| 03 | Facility Turnaround or Maintenance |
| 04 | Revised Delivery Point |
| 05 | Road or Weather Conditions |
| 06 | Field Tank Inventory - Included |
| 07 | Field Tank Inventory - Excluded |
| 08 | Shut-in Production |
| 10 | Change in Battery Operator |
| 11 | Change in Shipper Information |
| 12 | Forecast Error |
| 13 | Production Increase - Outside Production |
| 14 | Operational Problems at Battery |
| 15 | Royalty Revision |
| 99 | Miscellaneous - Requires Full Explanation |
12.7 Sample Confidentiality Agreement
Sample Confidentiality Agreement